Club Deal Mazhar Living – Progress report
Technology:
- Completion of earthworks in May 2023
- Installation of cranes and start of foundation work as soon as earthworks are completed
- Phase II technical studies underway
Keeping to the construction schedule and saving on construction costs as communicated to our co-investors
Commercial :
- Overall pre-bookings of over 70% of total stock – Actual bookings of almost 50% of total stock
- Sales rate of almost twenty units per month, ahead of the forecasts communicated to our co-investors.